18/06/2026
This project saved approximately $350,000 compared to a traditional concrete alternative.
Located in Newman, WA, this 4,500m² industrial hardstand was designed for a steel culvert and stormwater pipe manufacturer operating in one of Australia's most remote and demanding environments.
Using Rombus V2, the project was completed in just 9 days by a 7-person crew, including a peak pour of 1,250m² in a single day.
The installation used 468m³ less concrete than a traditional 150mm slab, avoided more than 140,000kg of CO₂ emissions, and utilised over 21,400kg of recycled Australian plastic.
✔ Approximately $350,000 saved
✔ 468m³ less concrete used
✔ Completed in 9 days
✔ No imported fill required
✔ No expansion joints
✔ No perimeter edging
✔ Supports continuous road train traffic and 16-tonne forklifts
A smarter way to build for demanding industrial environments.